Materials, Equipment, Warehouse
Good Usage on Tasks
How Good Usage records link materials to specific Tasks, closing the loop from design through procurement to installation.
Good Usage is the record that connects a specific material (Variant) to a specific Task on a project. It is the final link in a chain that runs from “we planned to install this pipe here” all the way to “this task consumed it.”
What Good Usage is
Section titled “What Good Usage is”When a Task requires a physical material, a Good Usage record is created. It captures:
| Field | What it means |
|---|---|
| Task | The specific Task that needs or consumed this material |
| Quantity | How many units of the material this Task needs or consumed |
| Technical Structure Good | Optional link to the Required Good entry on a Technical Structure node, connecting back to the project design |
| Technical Structure Node | Optional direct link to a Technical Structure node, used when the usage is not tied to a specific Required Good line |
| Procurement Request | Optional link to the demand record that sources this material — either a STOCK pull or a PURCHASE |
Why Good Usage matters
Section titled “Why Good Usage matters”Without Good Usage, you would know that a Procurement Request exists and that a Purchase was made — but you would not know which Task on the project actually used the material. Good Usage closes that gap.
This matters for:
- Task progress — field workers and project managers can see exactly which materials are assigned to each task
- Traceability — you can trace from any task back to the purchase order, or from any purchase order forward to the task that consumed the goods
- Cost attribution — procurement costs can be attributed to the specific task and by extension to the project’s Work Breakdown Structure
The full chain in one view
Section titled “The full chain in one view”Technical Structure Node └── Required Good (Variant: Steel Pipe DN100, qty 10) └── Procurement Request (STOCK or PURCHASE) └── Good Usage └── Task (e.g. "Install main distribution pipe, Segment A")Reading top to bottom:
- The Technical Structure node captures where something will be installed
- The Required Good records which Variant is needed at that node
- The Procurement Request handles sourcing — either pulling from stock or raising a Purchase
- Good Usage links that procurement demand to the specific Task
- The Task is where the material is physically consumed