Three ways GreenVee marks key moments in a project schedule — progress markers, go/no-go checkpoints, and meetings.
Beyond tasks and segments, GreenVee provides three dedicated record types for marking key moments in a project: Milestones, Gates, and Events. Each serves a distinct purpose.
Milestone
Section titled “Milestone”A Milestone is a pure timeline marker. It has no conditions attached — it simply says “we have reached this point in the project.”
| Field | What it means |
|---|---|
| Name | The milestone label (e.g. “Design Approved”) |
| Description | Longer details about what this milestone represents |
| Planned date | Either a working-time offset from the project’s planned start date, or a fixed date you pin directly — see Floating vs. fixed dates below |
| Actual | The timestamp recorded once the milestone is marked completed |
| Completed | Whether the milestone has been reached |
Milestones are ideal for recording significant delivery dates, handover points, or contractual deadlines.
A Gate is a formal checkpoint with internal pass/fail conditions. Unlike a milestone, a gate must be actively evaluated before the project can move forward.
| Field | What it means |
|---|---|
| Name | The checkpoint label (e.g. “Ready for Construction”) |
| Description | Longer details about what this gate checks |
| State | Current status of the gate: Open, Passed, or Failed |
| Planned date | Either a working-time offset from the project’s planned start date, or a fixed date you pin directly — see Floating vs. fixed dates below |
| Deal-breaker | Whether failing this gate blocks the entire project |
| Value | A free-text field for recording a note or measurement captured at review time |
| Risk Actions | Risk mitigation actions linked to this gate — each linked action must be resolved before the gate can be signed off (see Project Risks) |
Gates sit inside the project’s schedule just like milestones, but require active evaluation before the project can proceed.
Gates can also be archived to hide a resolved or abandoned gate from the active view without deleting it, and — like most GreenVee records — support soft deletion, so a deleted gate is removed from view but not immediately destroyed.
Milestone vs. Gate — a direct comparison
Section titled “Milestone vs. Gate — a direct comparison”| Milestone | Gate | |
|---|---|---|
| Has pass/fail conditions | No | Yes |
| Can be a deal-breaker | No | Yes |
| Links to Risk Actions | No | Yes |
| Records a value | No | Yes |
| Marks “we are here” | Yes | Yes (also blocks until passed) |
An Event is a digital or physical project meeting or site visit. Events give the project a record of when the team gathered, who was there, and what was discussed.
| Field | What it means |
|---|---|
| Title | The event label |
| Description | Longer details, e.g. an agenda |
| Type | Whether the event is digital (video call) or physical (on-site visit) |
| Planned date | Either a working-time offset from the project’s planned start date, or a fixed date you pin directly — see Floating vs. fixed dates below |
| Start time / End time | The time window the event occupies on its day |
| Location | Physical address or venue |
| Meeting URL | Link to a video call (for digital events) |
Attendees
Section titled “Attendees”Unlike the fields above, attendees aren’t stored directly on the Event — each invite is its own record linking the event to either a Project Member or a plain email address (for guests who aren’t project members). Each attendee record tracks an attendance state: Pending, Accepted, Declined, or Tentative.
Floating vs. fixed dates
Section titled “Floating vs. fixed dates”Milestones, Gates, and Events share the same scheduling toggle:
- Floating (default) — the item’s date is calculated automatically from the project’s planned start date, using a working-time offset (see Segments, Task Packages, Tasks & Subtasks for how offsets resolve to calendar dates). If earlier work in the schedule shifts, the computed date shifts with it.
- Fixed — turn on the Fixed date toggle to pin the item to an exact calendar date. It stops moving with the rest of the schedule, which is useful for hard external deadlines (e.g. a contractual sign-off date or a booked site visit).