The page „Übersicht“ is the organization's daily briefing: key KPIs, problem cases and a comparison of all portfolios.
What it is for
Section titled “What it is for”The overview answers within seconds: Are our portfolios on plan? Where is our capital working? Where do I need to look today? It is purely an evaluation. You edit nothing here; you jump from here into the details.
Where in the app
Section titled “Where in the app”Projekt & Portfolio › Übersicht (Overview). The page is a Scoreboard on organization level.
Key terms
Section titled “Key terms”- SPI (schedule performance index): Earned Value ÷ Planned Value. Above 1 = ahead of plan, below 0.9 = critical.
- Value CPI: Realized value (project benefit + order revenues) ÷ actual costs. Above 1 = more value created than money spent.
- Capital employed: Sum of the budgets.
- Business value: Economic benefit from order volume and project benefit.
How it works
Section titled “How it works”The page is structured from top to bottom:
- Header „Tagesbriefing“ (daily briefing) with date and one sentence on the situation, for example „Alle 5 Portfolios liegen im Plan“ (all 5 portfolios on plan) or „3 von 5 Portfolios liegen im Plan — X fällt zurück“ (3 of 5 portfolios on plan — X is falling behind). Next to it the number of portfolios, programs and projects.
- „Kapital & Rendite — wohin das Kapital arbeitet“ (capital & return — where the capital works): A bar shows the capital employed and, inside it, the business value; below it the total profit with its share of the capital. Plus four KPIs: „Kapitalrendite“ (return on capital), „Wert-Kapital-Verhältnis“ (value-to-capital ratio), „Strategische Budgettreue“ (strategic budget adherence, with a traffic-light dot) and „Anteil gescheiterter Projekte“ (share of failed projects). An info icon explains each formula.
- „Trends — Monatlicher Gewinn“ (trends — monthly profit): Lines for plan and actual over the months.
- „Was heute zählt“ (what counts today): Up to four cards with portfolios that need attention. Red means SPI or Value CPI below 0.9, yellow means in the band up to 1.0, neutral means no status report yet. The worst cases are on top. Below them follow the „Fehlgeschlagene Projekte“ (failed projects) with portfolio and actual costs, or a note that there are none.
- „Portfolio-Vergleich“ (portfolio comparison): A table with one row per portfolio, sorted by economic value. Columns: „Portfolio“, „Gewinn / Wert“ (profit / value), „Kosten / Budget“ (costs / budget), „Risikoexposition“ (risk exposure), „Budgetziel“ (budget target), „SPI“, „Value CPI“. Red portfolios are marked „Achtung“ (attention), inactive ones „inaktiv“ (inactive).
A click on a card or row opens the portfolio or project. If there is no portfolio yet, the page instead shows a getting-started screen „Willkommen bei Aligia“ (welcome to Aligia) with the steps create portfolio, structure programs, link projects.
Interplay
Section titled “Interplay”The values come from the Budget, Business Case, Risks/Opportunities and Status reports of the projects. For the details of a portfolio, switch to its Scoreboard.