Budget (budget)

The budget is the financial frame of exactly one cost item; budget goals on project, program and portfolio are separate orientation values.

The Budget stores the amount available to a cost item and optionally a goal for this cost item (project data). The project budget results from the budgets of all cost items; program and portfolio budgets are the sums of their projects.

Detail view of the cost item (Budgetplan › double-click): rows „Budgetziel“ (Budget goal) and „Budget“ with a pencil icon for editing. Totals in Guides › Program budget and Guides › Portfolio budget.

Field Technical Type Required Meaning Notes
Budget value Amount yes Available budget of the cost item Default 0; increases on approved budget request
Budget goal goal_value Amount no Target value of the cost item appears in the table and the card „Rest-Budget“ as „Ziel“
Currency currency Text yes Currency of the budget System: project currency at creation; display always uses the project currency
Related to Kind Required On archive On delete
Cost item has one (1:1) yes – cost item blocks deletion of the budget
Budget request has many – – deleted along
  • A value of 0 cannot be saved in the detail view; the input is only applied for an amount other than 0.
  • Approving a budget request adds the requested amount to value; withdrawing the approval subtracts it again. See Budget request and Rule: budget request.
  • Actual costs, planned costs and budget requests do not change the budget. Only approvals and manual inputs do.

Budget goal on project, program and portfolio

Section titled “Budget goal on project, program and portfolio”

In addition to the budget per cost item, Project, Program and Portfolio each carry a field Budget goal (budget_goal, amount, optional). It is entered in the dialogs „Neues Projekt“ (section „Budget & Wirtschaftlichkeit“, description „Geplantes Gesamtbudget.“), „Neues Programm“ and „Neues Portfolio“ and shown in the profile.

Level Display Computes with it
Project Profile, budget plan (column „Budgetziel“, card „Rest-Budget“ › „Ziel“), program budget list no client table; server KPIs budget deviation (budget goal − actual costs), budget adherence, working capital, EVM BAC
Program Profile, card „Rest-Budget“ › „Ziel“ (sum of the project budget goals) –
Portfolio Profile, card „Budget“ › „Ziel“ –

Project budget = Σ budget.value; remaining budget = budget − actual costs; forecast costs (portfolio) = actual + planned; capital employed (organization) = Σ of all budgets. See Budget KPIs.

Cost item · Budget request · Guides › Plan the portfolio budget