Reference & Data Model
Task (task)
The task is the plannable unit of work: with status, position and duration in the plan, assignment to a project member, a time window for the optimizer and a checklist.
Purpose
Section titled “Purpose”Staff and equipment usages (ch. 4), time tracking (ch. 5), comments (ch. 8) and dependencies hang off the Task. Its status drives project progress; its dates are set by the Gantt in early phases and, from Execution on, by the optimizer or by maintaining actuals. (Data type: planning data, work plan)
Where in the app
Section titled “Where in the app”Project › „Arbeitsbereich“ (Work area; list/Gantt, double-click opens the side panel with „Checkliste“, „Info“, „Updaten“, „Ressourceneinsatz“); Workmanagement › Meine Aufgaben / Aufgaben (table and board with status columns). See Guides › Work area, Guides › Tasks.
Fields
Section titled “Fields”| Field | Technical | Type | Required | Meaning | Notes |
|---|---|---|---|---|---|
| Title | name |
Text | yes | Task name | |
| Segment | segment_id |
Reference | yes | Parent segment | Selectable only on creation |
| Work package | task_package_id |
Reference | no | Optional group in the segment | Selectable only on creation |
| Status | state |
Selection | yes | Processing state | Default „Entwurf“ (Draft); see States |
| Assignee | assigned_member_id |
Reference (Project member) | no | Main responsible Project member | Can be set by the optimizer (system) when it allocates a person |
| Location | address |
Address | no | Work location of the task | |
| Description | description |
Text | no | ||
| Position / Duration | delta_start_ms / duration_ms |
Time (relative) | yes | Position in the plan relative to the segment and duration in working time | No input field; Gantt move/resize (early phases), otherwise system (optimizer). New tasks: 1 day |
| Actual start / end | scheduled_start_date / scheduled_end_date |
Date | no | Actual dates or committed optimizer dates | In the dialog only from Execution on; system on optimizer commit |
| Not before | not_before_date |
Date | no | Earliest start | Section „Zeitfenster (Optimierer)“ (Time window (Optimizer)) |
| Not after | not_after_date |
Date | no | Latest end; counts as the due date | Basis for „Überfällige Aufgaben“ (Overdue tasks) |
| Constraint reason | constraint_reason |
Text | no | Reason for the time window | |
| Delegated to | delegate_id |
Reference (User/Agent) | no | Delegation to an Agent | Properties bar in the side panel; opens the agent log |
Displayed but computed from other entities: planned/actual effort (Staff usage, Time log), participants, equipment, goods.
Subscribers (task_subscriber)
Section titled “Subscribers (task_subscriber)”Mapping table task ⇄ user. Via „Abonnenten hinzufügen“ (Add subscribers) in the context menu; deleted along with the task or the user.
Relations
Section titled “Relations”| Related to | Kind | Required | On archive | On delete |
|---|---|---|---|---|
| Project | belongs to | yes | archived along | deleted along |
| Segment | belongs to | yes | archived along | deleted along |
| Work package | belongs to | no | kept | reference cleared |
| Project member (assignee) | belongs to | no | kept | kept |
| User/Agent (delegate) | belongs to | no | kept | reference cleared |
| User (subscriber) | n:m | – | archived along | deleted along |
| Subtask, Comment | has many | – | archived along | deleted along |
| Dependency | endpoint | – | – | dependencies deleted along |
States
Section titled “States”| Value | Label | Meaning |
|---|---|---|
backlog |
Entwurf | Default on creation |
todo |
ToDo | Ready |
in_progress |
In Bearbeitung | |
in_review |
in Prüfung | |
done |
Erledigt | Counts as finished (progress) |
duplicate |
Duplikat | Sorted out |
cancelled |
Fehlgeschlagen | Sorted out |
Every status can be chosen directly at any time (status selection in the side panel, board columns, context menu); there is no enforced order. Only „Erledigt“ (Done) has a computational effect.
Rules & automation
Section titled “Rules & automation”- Creation only in early phases; from Execution on, maintain dates via „Tatsächlicher Start/Ende“ (Actual start/end) and the time window and re-optimize (see Guides › A date slips).
- The optimizer respects Not before/Not after; it does not reschedule completed tasks, and running tasks not before their start. On commit it writes position, duration, actual start/end and, if applicable, the assignee (Optimizer commit).
- Deleting a task deletes all dependencies attached to it.
Progress (share of done), open tasks (≠ done), overdue tasks (not_after_date < today), tasks by status: Progress, Counts, Work.