Resolving a resource conflict

How to identify, evaluate and resolve double bookings and collisions with absences.

No person and no equipment is scheduled multiple times at once or booked during an absence.

Portfolio manager/PMO (identifies), Team lead/coordinator and Project manager (resolve), for optimization runs Admin.

Tasks are assigned to resources. Absences and unavailabilities are maintained under Unavailabilities.

  1. Identify conflicts – In the Resource workload the summary at the top shows the number of conflicts. The conflict list names kind, resource, project, task and overlapping hours.
  2. Check unavailabilities – Under Unavailabilities the note shows how many assignments are affected by absences. The „Auswirkungen“ (impacts) of an unavailability list the affected tasks.
  3. Clarify priority – In the tab Strategy of the portfolio you see which of the involved projects has precedence.
  4. Check the team – In Resource planning you see org chart and workload of the affected project and identify possible substitutes.
  5. Resolve – The project manager changes the assignment or the dates of the task in the project under Resources or in the Work area.
  6. Alternatively optimize – With many conflicts, the „Portfolio-Optimierung“ (portfolio optimization) from the tab „Strategie“ shows bottleneck resources and a coordinated schedule. Starting and applying a run needs access to optimization.
  7. Check – The resource workload updates. Once the conflict is resolved, it disappears from the list.

The conflict list is empty or contains only consciously accepted overlaps. The workload is in the green or yellow range.