Planned personnel costs from resource planning (employee_usage.personal_cost)
Every employee usage on a task creates a continuously reconciled planned item „Personalkosten“.
Trigger
Section titled “Trigger”- Employee resource usage (
employee_usage) is created, changed (effort, count, project member, task) or deleted. - The task (
task) changes project. - The project hourly rate of the project member (
project_member.hourly_rate) changes. - The hourly rate of the employee (
employee.hourly_cost) changes; affects only members without their own project hourly rate.
Condition
Section titled “Condition”Usage and task exist (not deleted). The project has a cost item „Personalkosten“ (personnel costs). A rate can be determined: the member’s project hourly rate, otherwise the employee’s hourly rate. A rate of 0 is valid; without an employee and without a project hourly rate the rule skips.
What is created
Section titled “What is created”A planned item (planned_cost) on the cost item „Personalkosten“ of the task’s project:
Amount = est. effort (h) × count × hourly rateDate = creation date of the usageText = „Geplante Personalkosten aus Ressourcenplanung“Source = Ressourcenplanung · „<h> h <Mitarbeiter> — <Aufgabe>“Example: 40 h × 2 persons × 50 € = 4.000,00 €.
On change or rollback
Section titled “On change or rollback”Continuously reconciled: every change to effort, count, rate or task rewrites the amount. Deleting the usage or the task removes the planned item; restoring brings it back. The planned item persists for the entire project duration, also after times have been approved; plan and actual stand side by side.
Where visible
Section titled “Where visible”Project view › Wirtschaftlichkeit › Budgetplan, detail view of the cost item „Personalkosten“, section „Kosten“ (flag „Systemgeneriert“). The source is in Projektansicht › Ressourcen (Guides › Resources).
Known limitations
Section titled “Known limitations”- The date of the planned item is the creation date of the usage, not the planned period of the task.
- A usage without a staffed member (empty seat) and without a project hourly rate creates no planned item.
- Optimizer bookings (
employee_booking) create no costs; the usage alone is the basis.
See Employee resource usage · Planned item · Project member.