Submitting & deciding a budget request

Request additional budget for a cost type, decide the request and track the effect in project, program and portfolio.

Additional demand has been requested with justification and decided. Approved amounts are part of the cost type’s budget.

  • The project carries the affected cost type with a budget in the „Budgetplan“ (Budget plan) (see Budget & costs).
  1. Identify the need. In the „Wirtschaftlichkeit“ (Financial performance) tab, section „Budgetplan“, remaining budget, deviation and status traffic light per cost type show where money is running short.
  2. Submit the request. In the detail view of the cost type you create a „Neue Budgetanfrage“ (New budget request) in the „Budgetanfragen“ (Budget requests) section. It contains the „Zu beantragenes Budget“ (Budget to request) and an „Anfragenbeschreibung“ (Request description). The request starts as „Offen“ (Open) with the date „Beantragt am“ (Requested on).
  3. Get an overview of requests. Sub-tabs filter by „Alle“ (All), „Genehmigt“ (Approved), „Offen“ (Open), „Abgelehnt“ (Rejected) and „Zurückgezogen“ (Withdrawn). The total applies to the selected tab in each case.
  4. Decide. In the „Budgetantrag“ (Budget request) dialog, the deciding person sets the status to „Genehmigt“ or „Abgelehnt“. Aligia records the date under „Beantwortet am“ (Answered on). Who decides is governed by your organization; technically, anyone whose grant at the project allows it may.
  5. Effect on the budget. With „Genehmigt“, Aligia increases the budget of the cost type by the requested amount. If an approval is later revoked, it decreases again. The „Genehmigt“ column sums approved requests. „Beantragt“ (Requested) sums all requests, including rejected and withdrawn ones.
  6. Withdraw instead of delete. You set an obsolete request to „Zurückgezogen“. Deletion is not provided. The request remains stored in an audit-proof way.
  7. View from above. The program budget shows „Genehmigt“ and „Beantragt“ per project. The portfolio budget has the KPI card „Budgetanfragen“ with the requested total and the approved share. The „Budgetanfragen“ sub-tab lists all requests with project and cost type. From there, each request can be opened and decided.

A traceable history of all requests and an adjusted budget that feeds into program and portfolio totals.