Progress & dates

KPIs on work progress, dates and milestones; the basis is tasks, segments, milestones and the project dates.

KPI MP PF PG PJ Where Meaning Calculation Display
Progress / completion („Fortschritt“ / „Fertigstellung“) ✓ ✓ ✓ PJ: Scoreboard › KPI band, card „Umsetzung“; PG: Scoreboard › „Projekt-Gesundheit“; PF: Scoreboard › „Aufsicht“ Share of completed tasks of a project Server: 100 × number of tasks with state „Erledigt“ ÷ number of tasks of the project; excluding deleted and archived tasks; ÷ 0 → 0. PF oversight, program row: unweighted mean of the child projects in the view (0 without children) % · tile or bar
Delay (D) („Verzug (T)“) ✓ ✓ PJ: Scoreboard › briefing chip; PG: Scoreboard › „Projekt-Gesundheit“ Deviation of the currently scheduled project end from the target end Server: „Ende“ (scheduled_end_at) − „Geplantes Ende“ (target_end_date) in calendar days; decimals and negative values possible; a missing date → no value („—“) Days · number
Ø progress („Ø Fortschritt“) ✓ Program › Scoreboard › strip Unweighted average of the progress of the projects in the program Server rollup: Σ progress of the child projects ÷ number of child projects already calculated; archived included % (0 decimals) · tile
Schedule index („Terminindex“) ✓ Project › Scoreboard › briefing chip Relative deviation of the current duration from the target duration Server: ((end − start) − (target end − target start)) ÷ (target end − target start); exactly 0 is hidden as „—“ Ratio (2 decimals) · chip
Planned duration / current schedule („Geplante Laufzeit“ / „Aktuelle Planung“) ✓ Project › Scoreboard › status card; Profile › key data Target dates against rescheduled dates (planning/optimizer, no actual data) Direct fields „Geplanter Start/Ende“ (target_*) and „Start/Ende“ (scheduled_*) Date – date
Overdue tasks („Überfällige Aufgaben“) ✓ Project › Scoreboard › „Umsetzung“ Tasks not completed with a due date before today View: number of tasks with state ≠ „Erledigt“ and „Spätestens bis“ (notAfterDate) set and < today Count; red > 0
Milestones (completed / total) („Meilensteine“) ✓ Project › Scoreboard › „Umsetzung“ Completed milestones of the project Server: number of milestones (via segments) with „Abgeschlossen“ = yes; hint: ÷ number of all milestones Count · tile with hint
Next milestone („Nächster Meilenstein“) ✓ Project › Scoreboard › „Umsetzung“ Name of the next open milestone View: across all segments, the non-completed milestone with the smallest time distance Text
Segment progress („Segment-Fortschritt“) ✓ Project › Scoreboard › card „Segmente“; Profile › segments Task completion per segment View: tasks „Erledigt“ ÷ tasks of the segment × 100. Scoreboard: without tasks „Keine Aufgaben“; profile: 0 % % · progress bar („erledigt / gesamt Aufgaben“)
Duration (prioritization) („Dauer“) ✓ Portfolio › Strategy › table (+ footer Ø duration) Duration of an element in days View: (end, otherwise target end) − (start, otherwise target start) in days „n d“
Duration (radar) („Dauer“) ✓ Portfolio › Strategy › radar Duration in calendar years, relative to the maximum of the selection View: end year − start year + 1 (at least 1) Radar axis
  • Progress has exactly one definition on the server: projectProgress_in_pct.
  • Progress of the program row in the portfolio oversight is averaged in the view and can differ from the server value „Ø Fortschritt“ of the program scoreboard (the server value includes archived projects).
  • Delay counts calendar days, not working days, and can be negative (ahead of plan). The briefings only count delay > 0.
  • Duration carries the same label in table and radar, but days versus calendar years.