Traffic lights, briefings and sort orders that condense the state of an object; the basis is status reports, phases, delay and K.O. criteria.

KPI MP PF PG PJ Where Meaning Calculation Display
Status report traffic lights („Gesamt“ · „Arbeitsplan“ · „Kosten“ · „Ressourcenaufwand“ · „Risiko/Chance“ · „Engineering“) ✓ ✓ ✓ PF: Scoreboard › „Aufsicht“ „Status“, Operations › table, status reports of the planning objects; PG: Scoreboard › „Projekt-Gesundheit“ „Status“, status reports; PJ: Scoreboard › status card, Status reports › current report + table Manual assessment per dimension from the last status report View: last status report of the object → assessment green/yellow/red per dimension; missing = not assessed (grey); no report → „—“/grey 6 traffic light dots / pills
Phase („Phase“) ✓ ✓ ✓ PF: Operations/Preparation › column; PG: Scoreboard › „Projekt-Gesundheit“; PJ: Scoreboard › briefing chip Management phase of the object Raw field; badge color per phase Badge / chip
Trend (per dimension) („Trend“) ✓ ✓ PG/PJ: Status reports › current report; PJ: Scoreboard › status card Change versus the previous report View: severity green 0 < yellow 1 < red 2; current − previous < 0 → better (green), > 0 → worse (red), otherwise same; “not assessed” on either side → same; no previous report → no badge Trend badge (arrow + „war {Bewertung}“)
Sort order “worst first” (badness) („schlechteste zuerst“) ✓ ✓ PF: Scoreboard › „Aufsicht“ (row order); PG: Scoreboard › „Projekt-Gesundheit“ Order by need for action View. PF: red = 3, yellow = 1 per traffic light + 2 if value < 0 + 2 if budget deviation (budget goal) < 0 + (100 − progress) ÷ 100; programs first, children indented. PG: red × 3 + yellow + (delay > 0 ? 2) + (K.O. > 0 ? 3) Order (invisible)
Budget status (actual vs. budget) („Budget-Status“) ✓ ✓ PG: Budget › list; PJ: Budget plan › list Budget traffic light per row View: red if actual costs > cost item budget, otherwise green; row additionally highlighted red Traffic light dot
Budget status (forecast vs. budget) / business case status („Budget-Status“ / „Business-Case-Status“) ✓ ✓ PF: Budget › list „Status“; PF/PG: Business Case › table „Status“ Traffic light for forecast or expected profit View. Budget: red forecast > budget, yellow > 90 %, green otherwise. Business case: red if expected profit < 0, otherwise green Traffic light dot
Status distribution („Statusverteilung“) ✓ Project › Scoreboard › status card › summary Number of green/yellow/red in the last status report View: count over the 6 dimensions per assessment (“not assessed” not counted); bar width = count ÷ assessed dimensions Count per color + stacked bar
Portfolio signal / „Was heute zählt“ (organization) („Portfolio-Signal“) ✓ Overview › right column (max. 4 cards); Portfolio comparison (pill „Achtung“, suffix „· inaktiv“) Portfolios that need action View from server values: SPI (0 → unknown), Value CPI (0 only true if AC > 0). Red = SPI < 0.9 or CPI < 0.9; neutral = both unknown; yellow = SPI ≤ 1.0 or CPI ≤ 1.0; otherwise ok (not shown). Order red → yellow → neutral; inactive portfolio → „· inaktiv“ Cards with color, SPI/CPI 2 decimals; pill
Daily briefing (organization) („Tagesbriefing“) ✓ Overview › header line One-sentence status of all portfolios View: ≥ 1 red: „{n} von {m} Portfolios liegen im Plan — {X} fällt zurück“ (on track = portfolio with SPI/CPI value and not red; X = red portfolio with the smallest min(SPI, CPI)); 0 red and data: „Alle {m} … im Plan“; otherwise „noch keine Kennzahlen“ Sentence with colored segment
Portfolio briefing / „Was heute zählt“ (portfolio) („Portfolio-Briefing“) ✓ Portfolio › Scoreboard › header + „Balance“ › right column (max. 4 cards) Unremarkable and conspicuous top-level elements View: top level = programs + direct projects; red = at least one red traffic light in the last status report (without report = unremarkable); sentence „{n} von {m} Elementen unauffällig — {X} braucht Aufmerksamkeit“; card text „Budgetabweichung (Budgetziel) · Fortschritt“ Text; red cards
Program briefing („Programm-Briefing“) ✓ Program › Scoreboard › briefing header How many child projects are “on track” Project red if K.O. violations > 0 or delay > 0 (status report traffic lights deliberately do not count); X = red project with the highest badness; 0 projects → „Noch keine Projekte im Programm.“ Text, segment green/red
Project briefing („Projekt-Briefing“) ✓ Project › Scoreboard › briefing header Verdict sentence on the project state View, order: (1) K.O. criteria violated > 0; (2) red traffic lights in the last status report > 0; (3) delay > 0; otherwise „im Plan“ (if a report or delay value exists), otherwise „Noch keine Statusdaten“ Text, tone good/bad
  • Three sources for “red”: organization = Earned Value indices; portfolio = status report traffic lights; program = K.O. violations and delay; project = K.O., then traffic lights, then delay. An object can be red at one level and unremarkable at the next.
  • The program briefing ignores status report traffic lights; the sorting and the column „Status“ of the same view use them.
  • „Was heute zählt“ at organization level reports „noch kein Statusbericht“ for portfolios without SPI and Value CPI; what is meant is a missing Earned Value basis, not a missing status report.
  • The PG profile project card shows the program phase instead of the project phase.

See Status report, Assessment, Guides › Status report editor.