Risks & opportunities
KPIs on expected damage, expected opportunity value, measures and initiatives; the basis is risks, opportunities and their measures.
| KPI | MP | PF | PG | PJ | Where | Meaning | Calculation | Display |
|---|---|---|---|---|---|---|---|---|
| Risk exposure („Risikoexposition“) | ✓ | ✓ | ✓ | ✓ | MP: Portfolio comparison › column; PF: Scoreboard › tile 5, Oversight; PG: Scoreboard › strip + card „Risiko & Chance“; PJ: Scoreboard › band + zone „Risiko vs. Chance“ | Expected risk damage without measures | Server: Σ possible damage × probability of occurrence (%) ÷ 100 over all non-deleted risks of the project (including inactive; no measures). PG/PF: rollup (archived included) | € compact · tile/column; PG/PJ: red bar relative to max(risk, opportunity) |
| Probable damage („Wahrscheinlicher Schaden“ / „P(Schaden)“ / „Risikoschaden“ „Wahrscheinlich“) | ✓ | ✓ | ✓ | PF: Scoreboard › „Balance“ › scatter plot (X), Strategy › table/bars/radar; PG/PJ: Risks/Opportunities › card „Risikoschaden“ (sub) + risks table | Expected damage after the effect of measures | View, active risks only: max(0, occurrence % − Σ reduction % of the non-discarded measures) ÷ 100 × possible damage + Σ measure costs; program: Σ children | € · column/axis/tile sub | |
| Probable success („Wahrscheinlicher Erfolg“ / „P(Erfolg)“ / „Chancenerfolg“ „Wahrscheinlich“) | ✓ | ✓ | ✓ | PF: Strategy › table/bars/radar; PG/PJ: Risks/Opportunities › card „Chancenerfolg“ (sub) + opportunities table | Expected opportunity value after initiatives | View, active opportunities only: (occurrence % + Σ increase % of the non-discarded initiatives) ÷ 100 × possible success − Σ initiative costs (PF caps at 100 %, PG/PJ tables only max(0, …)) | € · column/tile sub | |
| Opportunity / opportunity success (expected) („Chance“ / „Chancenerfolg“) | ✓ | ✓ | PG: Scoreboard › card „Risiko & Chance“; PJ: Scoreboard › zone „Risiko vs. Chance“ | Expected opportunity success without initiatives | Server: Σ possible success × occurrence % ÷ 100 over all opportunities (including inactive); PG: Σ of the known child values in the view | € compact („+…“) · green bar | ||
| Net value („Nettowert“) | ✓ | ✓ | PG: Scoreboard › card „Risiko & Chance“; PJ: Scoreboard › „Risiko & Qualität“ | Opportunity success minus risk damage | Server: opportunity − risk exposure; PG: (Σ opportunity in the view, otherwise 0) − (rollup risk, otherwise 0); both unknown → „—“ | € · text; red < 0 | ||
| Risk damage (occurred / actual damage) („Risikoschaden“ / „Tatsächlicher Schaden“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › card „Risikoschaden“ (main value) + table | Damage that has already occurred | View: Σ „Eingetretener Schaden“ over active risks (independent of the table filter); table: raw field, empty → „Nicht eingetreten“; bar = occurred ÷ possible | € · card / column | ||
| Risk damage (possible / possible damage) („Risikoschaden“ / „Möglicher Schaden“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › card (sub „Möglich“) + table | Maximum damage on occurrence | View: Σ „Möglicher Schaden“ over active risks; table: raw field | € | ||
| Opportunity success (occurred / actual success) („Chancenerfolg“ / „Tatsächlicher Erfolg“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › card „Chancenerfolg“ + table | Opportunity value already realized | View: Σ „Eingetretener Erfolg“ over active opportunities; empty → „Nicht eingetreten“ | € | ||
| Opportunity success (possible / possible success) („Chancenerfolg“ / „Möglicher Erfolg“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › card (sub „Möglich“) + table | Maximum opportunity value | View: Σ „Möglicher Erfolg“ over active opportunities | € | ||
| Risk reduction by („Risikominderung um“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › risks table | Sum of the probability reduction by measures | View: Σ reduction % of the measures with state ≠ „Verworfen“; not limited to 0–100 | % | ||
| Measure costs („Maßnahmenkosten“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › risks table | Costs of the measures per risk | View: Σ costs of the measures with state ≠ „Verworfen“ | € | ||
| Opportunity increase by / initiative costs („Chancenerhöhung um“ / „Initiativenkosten“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › opportunities table | Effect and costs of the initiatives per opportunity | View: Σ increase % or Σ costs of the initiatives with state ≠ „Verworfen“ | % / € | ||
| Risk/opportunity raw attributes („Eintritt (%)“, „Priorität“, „Schadensausmaß“ / „Erfolgsgrad“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › tables | Assessment attributes per risk/opportunity | Raw fields | %, number, text; damage extent „Hoch“ red / „Mittel“ yellow / „Niedrig“ green | ||
| Risk-opportunity matrix („Risiko-Chancen-Matrix“) | ✓ | ✓ | PG/PJ: Risks/Opportunities › matrix | Position of active risks/opportunities by probability and value | View, active only: X = occurrence %, Y = possible damage/success; cell severity = (p ÷ 100) × (value ÷ max), bands ≤ 0.2 green, ≤ 0.5 yellow, otherwise red (slider); tooltip „Erwartungswert ohne Maßnahmen“ = p ÷ 100 × value | Scatter plot over heatmap | ||
| Total costs of measures / initiatives („Gesamtkosten der Maßnahmen / Initiativen“) | ✓ | Project › Insights › „Maßnahmen & Initiativen“ | Cost sum of all measures or initiatives of the project | View: Σ costs with state ≠ „Verworfen“ (including filtered-out ones) | € | |||
| Risk heatmap (3×3) („Risiko-Heatmap“) | ✓ | Project › Scoreboard › „Risiko & Qualität“ | Number of risks per damage extent × probability grade | View: count over damage extent (X) and probability grade (Y), all risks (including inactive); color level relative to the maximum | 3×3 grid with count |
- Risk exposure ≠ probable damage. The server KPI takes all risks (including inactive) without measures; the risks tab and the scatter plot take only active risks, subtract the reduction and add measure costs. Same vocabulary, different number. Likewise: heatmap in the scoreboard without the active filter, matrix in the tab active only.
- Reduction above 100 %: the table column „Risikominderung um“ can show more than 100 %; in the damage formula the probability is limited to 0.
- Program: „Chance“ and „Nettowert“ mix a server rollup (risk, with archived projects) with a sum from the view (opportunity, without archived).
See Risk, Measure, Opportunity, Guides › Risk-opportunity matrix.