Planned cost (planned_cost)

A planned cost is an expected cost position; the system keeps its own planned costs continuously up to date.

Planned costs form the cost forecast of a cost item (project data). They are entered manually or derived by the system from resource planning, procurement requests and risks. Unlike cost events they are not a journal: manual rows can be changed freely, system rows are updated along with their source.

Detail view of the cost item › section „Kosten“ (Costs) › list „Plan-Positionen“ (Planned costs) with totals row, „+“ („Plan-Position hinzufügen“, Add planned cost), context menu „Details“ / „Löschen“ (Delete). Double-click opens the dialog „Plan-Position“. See Guides › Financial performance.

Field Technical Type Required Meaning Notes
Amount cost_value Amount yes Expected costs System rows: locked
Occurred on occurred_at Date yes Date of the expected costs cannot be changed after creation
Description description Text yes (may be empty) Label System rows: provenance text instead of description
Creation kind generated_from_system Yes/No yes „Manuell“ (manual, blue) or „Systemgeneriert“ (system-generated, grey) System
Source rule_key, source_id Reference no Rule and source row System; shown as text and link
Related to Kind Required On archive On delete
Cost item belongs to yes archived along deleted along
Project belongs to yes archived along deleted along
  • Manual planned costs: amount and description editable, deletion allowed. System rows: immutable for users; the server rejects every change. The creation kind can never be set to „Systemgeneriert“.
  • Generating rules (kept in sync: source changed → new amount, source deleted → planned cost gone):
    • Employee usage → „Geplante Personalkosten aus Ressourcenplanung“ (planned personnel costs from resource planning) (Rule)
    • Purchase request → „Geplante Materialkosten aus Einkaufsaufforderung“ (planned material costs from purchase request); stock request, while „offen“ (open) → „Materialkosten aus Lagerentnahme“ (material costs from stock withdrawal) (Rule)
    • Active risk → „Erwartete Risikokosten“ (expected risk costs) = damage value × (probability − prevention reduction) (Rule)

Card „Geplante Kosten“ (Planned costs) = Σ planned costs; column „Geplant“ = max(0, planned − actual) per cost item; forecast costs (portfolio) = actual + planned. See Budget KPIs.