Building & optimizing the work plan
Build a structure of segments, tasks and milestones, link them and have the optimizer schedule them.
A complete work plan that respects dependencies, is feasible with the available resources and is adopted as a binding schedule.
Who is involved
Section titled “Who is involved”- Project manager – builds the plan.
- Team lead/coordinator – supplies efforts and resource requirements.
- Admin – starts optimization runs and applies the result.
Prerequisites
Section titled “Prerequisites”- The project is in „Initialisierung“ (Initialization), „Definition“ or „Planung“ (Planning). Planning objects can only be created in these phases.
- Team and resource requirements are recorded at least roughly (see Assembling the team).
The workflow
Section titled “The workflow”- Create segments. In the „Arbeitsbereich“ (Work area) tab, segments divide the project into sections, such as construction stages or trades. All other planning objects belong to a segment.
- Add planning objects. Per segment you create tasks, work packages (bundles of tasks), milestones, gates (checkpoints with a decision) and events. The list view shows the progress per segment as the share of completed tasks.
- Resource deployment per task. In the task, the „Ressourceneinsatz“ (Resource deployment) section records which workers, which equipment and which goods are needed. From this, the optimizer calculates workload and material requirements.
- Draw dependencies. The „Gantt-Arbeitsplan“ (Gantt work plan) shows all objects on a timeline. In the early phases it works relatively („Tag N“, Day N), and you connect tasks, milestones and gates directly into dependencies (see Gantt).
- Optimize. The „Optimierer“ (Optimizer) button in the header of the project view opens the „Projekt-Optimierung“ (Project optimization). It compares „Aktueller Plan → Optimierter Plan“ (Current plan → Optimized plan), shows bottlenecks, resource workload, material requirements and order proposals. With fixations you play through “what-if” variants without saving anything.
- Apply. „Übernehmen“ (Apply) commits the optimized schedule: tasks receive real dates, resource bookings and procurement requests are created, and the project switches to the „Umsetzung“ (Execution) phase.
Result
Section titled “Result”A committed schedule. From „Umsetzung“ onward, the Gantt work plan shows real calendar dates and is read-only. The structure is frozen; date changes go through a new optimization.
See also
Section titled “See also”Gate decision & phase change · From engineering to order · Resolving a resource conflict · Lifecycle bar