Employee booking (employee_booking)

An employee booking is a concrete period in which an employee is scheduled for an employee usage.

The booking turns the estimated effort into an appointment: from date/time to date/time. Bookings are the basis of workload and of conflict checking across all projects. They are created manually or by the Optimizer. (Transactional data)

Task › „Ressourceneinsatz“ (Resource usage) › expand a row: sub-rows „Buchung“ (Booking) with start, end and hours. „Buchung hinzufügen“ (Add booking, plus) opens „Neue Buchung“ (New booking); context menu „Bearbeiten“ (Edit) → „Buchung bearbeiten“ (Edit booking), „Löschen“ (Delete). Across projects in the resource Gantt under Projekt & Portfolio › Ressourcenauslastung (Resource workload) (Guides › Resource workload) and in the project’s „Auslastungen“ (workloads).

Field Technical Type Required Meaning Notes
Start (date) start_at Date yes First day
Start (time) start_time Time no Start on the first day dialog requires a time
End (date) end_at Date yes Last day „Startdatum ist Enddatum“ (start date is end date) sets end = start
End (time) end_time Time no End on the last day Without times the booking counts 0 hours
Project member / Task via employee_usage_id Reference yes Displayed in the dialog
Employee employee_id Reference yes Booked person System: from the project member

Not displayed: optimization_run_id (system, server only; marks Optimizer bookings).

Related to Kind Required On archive On delete
Employee usage belongs to yes archived along deleted along
Employee belongs to yes — deleted along
  • Only filled roles can be booked.
  • Optimizer: When a run is applied, all earlier Optimizer bookings of the project are replaced; manual bookings remain untouched. Rolling back removes Optimizer bookings only (Optimizer commit).
  • Conflicts: Two bookings of the same person that overlap, or a booking within an absence, produce a resource conflict (Guides › Resolve a resource conflict).
  • The sum of booked hours appears in „Plan-Aufwand“ as a second value („Geschätzter Aufwand / Summe der gebuchten Stunden“ — estimated effort / sum of booked hours).

Utilization % (scheduled ÷ available), resource conflicts, current utilization on the team node – see Resources & workload.