Guides
Scoreboard & KPI tiles
The Scoreboard is the KPI home page of every level: a briefing sentence, condensed KPIs and pointers to what needs attention.
What it is
Section titled “What it is”A Scoreboard summarizes the state of a project, program, portfolio or the whole organization on one page. It is read-only. You do not maintain data there; you read the effect of your data.
Where it appears
Section titled “Where it appears”- Project, tab „Scoreboard“ (home page of the project): Project Scoreboard
- Program, tab „Scoreboard“: Program Scoreboard
- Portfolio, tab „Scoreboard“: Portfolio Scoreboard
- Projekt & Portfolio › Übersicht: organization-wide dashboard, see Overview
- Workmanagement › Übersicht with „Meine Übersicht“ (my overview) and „Organisation“: uses the same building blocks, see Work management
Structure
Section titled “Structure”All Scoreboards are built from the same building blocks:
| Building block | Purpose |
|---|---|
| Briefing („Tagesbriefing“, „Portfolio-Briefing“, „Programm-Briefing“, „Projekt-Briefing“) | One sentence on the situation, e.g. how many elements are on plan and who is falling behind |
| KPI bar | Single values as tiles, e.g. profit, working capital, risk exposure, SPI, Value CPI |
| Topic cards | Groups per topic: for the project „Umsetzung“ (Execution), „Finanzen“ (Finance), „Risiko & Qualität“ (Risk & quality), „Earned Value“; for the program „Budget“, „Ertrag“ (Earnings), „Risiko & Chance“ (Risk & opportunity) |
| Comparison tables | „Portfolio-Vergleich“ (portfolio comparison) or „Projekt-Gesundheit“ (project health) with traffic lights and bars per row |
| Attention cards („Was heute zählt“, what matters today) | The most conspicuous elements with a direct jump to them |
How to work with it
Section titled “How to work with it”- Look up formulas: Next to many KPIs is an info icon. It explains how the value is calculated, e.g. „Terminindex (SPI) = Earned Value ÷ Planned Value“.
- Read colors: For KPIs such as SPI and Value CPI, „Rot unter 0,9 · Gelb 0,9–1,0 · Grün über 1,0“ applies (red below 0.9 · yellow 0.9–1.0 · green above 1.0). Costs against budget turn yellow from 90 % and red above 100 %.
- Jump onward: Rows and attention cards lead to the affected portfolio, program or project.
- Freshness: KPIs are automatically recalculated in the background as soon as the underlying data changes. There is no refresh button. Newly created organizations initially see placeholders such as „Noch keine Daten“ (no data yet).
Specifics per view
Section titled “Specifics per view”The project Scoreboard additionally shows the traffic lights of the last status report with „Statusberichte ansehen“ (view status reports) and a „Risiko-Heatmap“. Portfolio and program condense the projects below them; the „Status“ column shows the traffic lights of the respective latest status reports. The Overview compares portfolios by capital and return. The Work management overview shows personal workload instead of financial KPIs.