The tab „Gantt“ shows all programs and projects of the portfolio on a shared timeline.

You see overlaps, dependencies over time and the workload of the portfolio over time. This helps to set start dates of new initiatives sensibly.

Projekt & Portfolio › Portfolios › Portfolio › tab „Gantt“. You find the same display across portfolios in the Multi-project board.

  • „Ist-Modus“ (actual mode): all initiatives at their actual dates.
  • „Plan-Modus“ (plan mode): only initiatives without fixed dates, on a relative timeline.
  • Fixed dates: start and end that were set as binding by an applied optimization.

At the top right you switch between „Ist-Modus“ (blue) and „Plan-Modus“ (orange) via a toggle. The view opens in actual mode.

  • In actual mode all programs with their projects as well as standalone projects appear. Fixed dates take precedence. If they are missing, Aligia uses the target dates; such bars are grey and marked „(Plan)“. Initiatives without any dates are missing.
  • In plan mode you see only initiatives without fixed dates. The timeline is relative, and the display can be edited. This way you play through sequences before dates are fixed.

Operation, zoom and display are described in the tool Gantt.

  • The Multi-project board shows the same with portfolio selection.
  • Fixed dates typically arise via the „Portfolio-Optimierung“ (portfolio optimization) in the tab Strategy.
  • For the people behind the bars use the Resource workload.