Milestone (milestone)

A milestone is a point in time without duration in a segment that is marked as reached.

Milestones mark key dates in the work plan. They have a planned day, an optional hard time window for the optimizer and a reached flag. (Data type: planning data, work plan)

Project › „Arbeitsbereich“ (Work area) › „Neuer Meilenstein“ (New milestone; in the „Neu“ menu or from the segment row); in the Gantt as a point in time; in the scoreboard „Nächster Meilenstein“ (Next milestone) and „Meilensteine (abgeschlossen / gesamt)“ (Milestones (completed / total)). See Guides › Work area.

Field Technical Type Required Meaning Notes
Title name Text yes
Segment segment_id Reference yes (dialog) Parent segment
Planned on delta_ms Date (from relative position) yes Planned day Stored as offset from the segment start; empty on creation = after the last object of the segment; Gantt move and optimizer (system) change it
Not before not_before_date Date no Earliest date
Not after not_after_date Date no Latest date
General description description Text no
Reached is_completed Yes/No yes „Meilenstein als erreicht markieren“ (Mark milestone as reached) Toggle in the milestone view and in the context menu
Related to Kind Required On archive On delete
Segment belongs to no (technically) archived along deleted along
Dependency endpoint – – dependencies deleted along

is_completed: not reached („Offen“, Open) / reached. Toggled manually; no automation sets it.

  • Creation only in early phases.
  • On optimizer commit, milestones follow the tasks they are attached to via dependencies (Optimizer commit).

„Meilensteine (abgeschlossen / gesamt)“ (Milestones (completed / total)), „Nächster Meilenstein“ (Next milestone; next open one by time offset): Progress.