Applying and rolling back an optimization (system_optimize_commit, system_optimize_rollback)
„Übernehmen“ writes a solved optimization run bindingly into project, tasks, bookings and procurement; the rollback undoes that for the future.
Trigger
Section titled “Trigger”„Übernehmen“ / „Alle übernehmen“ (apply / apply all) in the portfolio or project optimization (Guides › Schedule the portfolio with the optimizer). Rollback: phase change back to an early phase after confirming „Optimierung verwerfen?“ (Phase rules).
Condition
Section titled “Condition”- An access on the whole organization that allows optimization (for example base access „Bearbeiten“, Edit); otherwise „Du hast keinen Zugriff zum Übernehmen.“ (You have no access to apply this.)
- The project is „Aktiv“ (not „Pausiert“, „Erfolgreich abgeschlossen“ or „Fehlgeschlagen“) and not in „Abschluss“.
- The run is the most recent; with a newer run: „Veraltet — neu berechnen“.
- No repeated apply with exactly the same options („already applied — roll back first“); an apply with new options (e.g. first dates, later bookings) is allowed.
What changes (depending on the chosen options)
Section titled “What changes (depending on the chosen options)”| Area | Effect |
|---|---|
| Tasks, segments | Relative positions (deltas) and „Geplanter Start/Ende“ (scheduled_start_date/end_date) from the solution plan; gates/milestones with their segments |
| Task → assignment | assigned_member_id = first assigned project member |
| Bookings | Employee booking / equipment booking per (task, resource); earlier optimizer bookings of the project are replaced, manual ones never touched |
| Procurement | Per order proposal one procurement request of type purchase, status „Offen“, with run identifier; earlier open optimizer requests are replaced; user-created or already completed ones remain |
| Project | „Geplanter Start/Ende“ (scheduled_start_at/end_at) set to the solved window (only when applying dates) |
| Phase | From „Initialisierung“, „Definition“ or „Planung“ forward to „Umsetzung“; never downward; only if a date or booking option is chosen (a pure procurement apply does not change the phase) |
| EVM | The phase change to „Umsetzung“ freezes the baseline (project_baseline, version 1), see EVM |
| Run | Apply timestamp, number of booking conflicts and a before-snapshot of all overwritten values are stored on the run |
Follow-on effect: the new procurement requests create planned items „Materialkosten“ (Procurement).
On rollback
Section titled “On rollback”The rollback (needs access to optimization, active project only) undoes all applied runs of the project in one transaction, newest first:
- Dates, positions, assignments and project window are reset from the snapshot – only where the value still matches the applied one; subsequent manual changes remain and are counted.
- Future optimizer bookings (from today, UTC day) are removed, running ones are cut off at the previous day; the past remains.
- Open optimizer procurement requests are deleted (completed ones remain).
- The EVM baseline is released if the apply had created it.
- The phase is set to the chosen early phase. If there is no applied run, the phase is simply set directly.
Where visible
Section titled “Where visible”Gantt (workspace, read-only from „Umsetzung“ on), Projektansicht › Ressourcen (bookings), › Beschaffung, phase badge, activity („Optimierung zurückgesetzt“).
Known limitations
Section titled “Known limitations”- The optimizer plans with scheduled persons, availability and material; skills are not matched.
- Apply and rollback cannot be undone; the rollback removes no manual bookings.
- A project with an applied run cannot be deleted; roll back the optimization first (Locks & delete protection).
See Optimization · Employee booking · Equipment booking · Procurement request.