Guides
From engineering to order
The technical structure yields components, components yield material requirements, and these yield procurement requests and purchases.
All technically required goods are specified, assigned to the tasks and procured in time via stock or purchasing.
Who is involved
Section titled “Who is involved”- Engineer/technician – maintains structure and requirements.
- Project manager – assigns material to the tasks and keeps an eye on dates.
- Procurement – processes procurement requests and purchases.
Prerequisites
Section titled “Prerequisites”- A technical structure is assigned to the project. Without a structure, the „Engineering“ tab only offers „Tech-Struktur hinzufügen“ (Add tech structure).
- The goods are recorded in the material catalog with material type and technical data.
The workflow
Section titled “The workflow”- Outline the structure. In the „Engineering“ tab, the technical structure consists of structure folders (nodes), „Technischen Komponenten“ (Technical components) and „Komponentenanforderungen“ (Component requirements).
- Formulate requirements. If the concrete good is not yet determined, a component requirement describes the demand via „Technische Anforderungen“ (Technical requirements) with conditions per specification (=, ≥, ≤, „zwischen“ (between), „einer von“ (one of)).
- Find a suitable good. „Spec-Matching“ checks goods against the requirements. The selected component permanently replaces the requirement; this step is not reversible.
- Assign material to the tasks. Under „Allokation“ (Allocation) of a component you define which quantity is consumed in which tasks. This way the material appears in the „Ressourceneinsatz“ (Resource deployment) of the task and in the material requirement of the optimizer.
- Trigger procurement. A procurement request is either a „Lageraufforderung“ (Stock request, from inventory) or an „Einkaufsaufforderung“ (Purchase request), with quantity, delivery address, „Frühstens am“ (Earliest on) and „Fällig am“ (Due on). It is created on the component, manually in the „Beschaffung“ (Procurement) tab or automatically from the order proposals when applying an optimization.
- Process the purchase. In the „Beschaffung“ tab, procurement manages the „Einkäufe“ (Purchases) with unit price, quantity, discount and tax rate. The status ranges from „Entwurf“ (Draft) via „Bestellt“ (Ordered) and „Geliefert“ (Delivered) to „Bezahlt“ (Paid). KPIs show „Bereits eingekauft“ (Already purchased), „Einkaufsvolumen“ (Purchase volume) and the number of procurement requests.
Result
Section titled “Result”Material is specified, scheduled and ordered. Procurement transactions appear as system-generated actual bookings in the budget plan.
See also
Section titled “See also”Building the material catalog · Materials · Budget & costs · Procurement