Risk and opportunity costs (risk.*, risk_action.opex, chance_action.opex)
Active risks create a continuous planned item; occurred risks and measures on occurred risks/opportunities create actual bookings on „Sonstige betriebliche Aufwendungen“.
Trigger
Section titled “Trigger”- Risk (
risk): damage value, probability, active flag, project, „Eingetreten am“ (occurred on), occurred damage. - Risk measure (
risk_action) / opportunity measure (chance_action): type, status, costs, probability reduction, assignment. - Opportunity (
chance): „Eingetreten am“ (for opportunity measures).
Condition and result
Section titled “Condition and result”A · Expected risk costs (risk.expected_opex, continuous):
Risk is active and not deleted; cost item „Sonstige betriebliche Aufwendungen“ (other operating expenses) present.
effective probability = max(0, probability % − Σ reduction % of all prevention measures except „Verworfen“)Amount = possible damage × effective probability / 100Date = creation date of the risk · text „Erwartete Risikokosten“Example: 10.000 € × (55 % − 15 %) / 100 = 4.000,00 €. If the measures reduce the probability to 0 or below, the planned item is 0,00 €. Deactivating or deleting removes it.
B · Risk occurred (risk.occurred_opex, created once):
„Eingetreten am“ and occurred damage value are set; cost item present. Actual booking for the occurred damage, date = „Eingetreten am“, text „Risiko eingetreten“. Later changes to either field do not change the booking.
C · Measure costs (risk_action.opex, chance_action.opex):
Measure of type prevention or reaction, status not „Verworfen“, parent risk/opportunity has occurred („Eingetreten am“ set). Actual booking for the measure’s „Kosten“ field. Date: for prevention the creation date of the measure, for reaction the occurrence date of the risk/opportunity. Source: „Risiko-Prävention/-Reaktion · <Maßnahme> (
On change or rollback
Section titled “On change or rollback”A is recomputed on every change to the risk or prevention measures. B remains unchanged after the first booking. C: the booking is created on the first event that meets the condition; later changes to the measure’s costs or status are not carried over to the existing booking (see limitations).
Where visible
Section titled “Where visible”Cost item „Sonstige betriebliche Aufwendungen“, section „Kosten“. Sources in Projektansicht › Risiken (Guides › Risks & opportunities); the risk card shows the effective probability in the tooltip („Effektiv: … %“).
Known limitations
Section titled “Known limitations”- Prevention measures are only booked once the risk has occurred – not when the measure is carried out.
- Rule C is technically configured as “continuously reconciled”, but its target (actual booking) is unchangeable. A later change to the measure costs or a discard therefore triggers a failing background run; the data remains unchanged. Correction only via reversal.
- Opportunities create no planned item (no counterpart to A).
See Risk · Risk measure · Opportunity · Opportunity measure.