Earned Value (catalog)

The five Earned Value KPIs in catalog format; formulas and prerequisites are explained on the page „Earned Value (EVM)“.

All values on this page are calculated and stored by the server; they depend on the calendar day and are additionally refreshed every 5 minutes.

KPI MP PF PG PJ Where Meaning Calculation Display
SPI („SPI“) ✓ ✓ ✓ ✓ MP: Portfolio comparison › „SPI“, „Was heute zählt“; PF: Scoreboard › tile 6; PG: Scoreboard › strip; PJ: Scoreboard › „Earned Value“ (only from phase „Umsetzung“) Schedule performance index: Earned Value ÷ Planned Value Per project: PV = BAC × elapsed share of the frozen plan window (today, calendar days); EV = BAC × weight of completed tasks ÷ total weight (0/100; weight = effort × hourly rate); BAC = budget goal, otherwise Σ cost item budget; without baseline EV = PV = 0. PG/PF/MP: Σ EV ÷ Σ PV over non-archived, non-deleted child projects; PV 0 → „—“ Ratio (2 decimals) + traffic light dot; PJ: scale 0–2, mark 1.0
Value CPI („Value CPI“) ✓ ✓ ✓ ✓ MP: Portfolio comparison › „Value CPI“, „Was heute zählt“; PF: Scoreboard › tile 7; PG: Scoreboard › strip; PJ: Scoreboard › „Earned Value“ Realized value per euro spent Per project: (benefit + Σ earning occurrences with date ≤ today) ÷ AC; AC = Σ cost occurrences with date ≤ today; AC 0 → 0. PG/PF/MP: Σ value ÷ Σ AC over non-archived children. No baseline needed; PJ tile only if actual costs > 0; MP: 0 at AC > 0 stays 0 (true zero), otherwise „—“ Ratio (2 decimals) + traffic light dot
Planned value (PV) („Plankosten“) ✓ ✓ PJ: EAC tile hint; MP: SPI tooltip Planned Value as of the reference date BAC × elapsed share of the frozen plan window (linear); portfolio = Σ children. Not a real cost plan €
EAC („EAC“) ✓ Project › Scoreboard › „Earned Value“ Forecast total costs AC + (BAC − EV) ÷ work-based CPI, with work-based CPI = EV ÷ AC (not the displayed Value CPI); CPI 0 → „—“ € · tile (hint „Plankosten“)
Earned Value (EV) / AC (EVM) ✓ Overview › Portfolio comparison › tooltips SPI/Value CPI Building blocks of the indices EV = Σ EV of the children; AC = Σ AC (EVM definition, up to today, non-archived projects) € (tooltip)
  • All EVM tiles „—“: the project has no baseline yet (phase before „Umsetzung“, missing target dates, budget goal and cost item budget 0, no efforts with an hourly rate). Value CPI still appears as soon as actual costs are booked.
  • Two actual cost definitions in the portfolio comparison: „Kosten / Budget“ uses the actual costs without date filter (archived included); the Value CPI tooltip uses AC per EVM definition (up to today, excluding archived projects). The tooltip EV is back-calculated as Value CPI × AC.
  • Value CPI 0 with booked costs is rated red (true zero: no benefit, no earnings), whereas SPI 0 is shown as „—“. The neutral text „noch kein Statusbericht“ (no status report yet) in „Was heute zählt“ refers to missing EVM values, not to status reports.
  • The SPI/Value CPI tooltips at program level use the texts of the organization level („Portfolio = Summe …“).