Creating a status report
Regularly assess the project status in six traffic light areas and make it visible for program and portfolio.
A current status report with a traceable assessment per area and a recognizable trend compared to the previous report.
Who is involved
Section titled “Who is involved”- Project manager – creates the report.
- Program manager, portfolio manager/PMO, executive management – read it in consolidated form.
Prerequisites
Section titled “Prerequisites”- Plan, budget and risks are maintained so that the assessment is based on data.
The workflow
Section titled “The workflow”- Review the situation. The Scoreboard, the Work area, Financial performance, Risks/Opportunities and Engineering provide the facts.
- Create the report. In the „Statusberichte“ (Status reports) tab you create a „Neuen Statusbericht“ (New status report) with a title.
- Assess the areas. For „Gesamt“ (Overall), „Arbeitsplan“ (Work plan), „Kosten“ (Costs), „Ressourcenaufwand“ (Resource effort), „Risiko/Chance“ (Risk/Opportunity) and „Engineering“ you assign an „Einschätzung“ (Assessment: green, yellow, red) and a „Kommentar“ (Comment) each.
- Read the trend. The most recent report appears as „Aktueller Statusbericht“ (Current status report). Per area, Aligia shows the trend compared to the „Vorbericht“ (Previous report). The table below lists all reports with their traffic lights.
- Pass it on. The current state appears on the project scoreboard. Programs and portfolios show the reports of their projects collectively (see Reporting program status).
Result
Section titled “Result”A continuous report history that makes deviations visible early and feeds the program and portfolio views.