The cockpit of the program: briefing, KPIs, finances and the health of each project on one page.

The scoreboard answers the question: “Is my program on track, and which project needs attention?” It is the program variant of the Scoreboard tool.

Program view, tab „Scoreboard“.

  • On track: no delay and no failed deal-breaker gate. The traffic lights of the status reports do not count for this.
  • K.O.: failed deal-breaker gates. A K.O. gate leads to project abort if it fails.
  • SPI / Value CPI: schedule and value index. Above 1 is good, below 0.9 critical.

The scoreboard has four areas:

  1. Program briefing: a sentence like “3 of 4 projects are on track — project X needs attention”. The project named is the one with the worst overall picture of red and yellow traffic lights, delay and K.O.
  2. Program KPIs: „Ø Fortschritt“ (Ø Progress: unweighted average over all projects), „Wirtschaftl. Programmwert“ (Economic program value: sum of order volume and benefit of the projects), „Working Capital“ (sum of the project budgets), „Risikoexposition“ (Risk exposure), „Budgetabweichung“ (Budget deviation), „SPI“ and „Value CPI“.
  3. Three cards: „Budget“ (budget, actual, outstanding, remaining budget), „Ertrag“ (Earnings: income, benefit, current costs, profit) and „Risiko & Chance“ (Risk & Opportunity) with the net value (opportunity success minus risk damage).
  4. Project health: a table of all projects with phase, status traffic lights, progress, value, profit, delay (D), budget vs. actual and K.O. The projects with the worst overall picture are at the top.

Every figure is a sum or an average over the projects of the program. An info hint on the KPI explains the respective formula.