Guides
Gate decision & phase change
Evaluate gates and deliberately guide the project through its lifecycle phases, forward as well as backward.
Gates are decided, and the project phase reflects the actual state.
Who is involved
Section titled “Who is involved”- Project manager – prepares and sets the phase.
- Portfolio manager/PMO or executive management – typically decide at gates.
- Whoever has access to optimization – for changes that apply or revert an optimization.
Prerequisites
Section titled “Prerequisites”- Gates are created in the Work area (see Building & optimizing the work plan).
The workflow
Section titled “The workflow”- Evaluate the gate. A gate is a checkpoint in the plan. Its status is open, „Bestanden“ (Passed) or „Verfehlt“ (Failed). A gate can be marked as a deal-breaker („Projektabbruch bei Fehlschlag“, Project abort on failure). Preventive and reactive measures can be attached to the gate.
- Signal on the scoreboard. A failed deal-breaker gate appears as a warning on the project’s Scoreboard and on the program’s scoreboard. It does not automatically trigger the phase change or closing as „Fehlgeschlagen“.
- Choose the phase. The phase badge in the header of the project view opens „Phase wählen“ (Choose phase) (see Lifecycle bar). The phases are „Initialisierung“ (Initialization) → „Definition“ → „Planung“ (Planning) → „Umsetzung“ (Execution) → „Abschluss“ (Closing). The phase can only be chosen for an active project; you do not set „Erfolgreich abgeschlossen“ (Succeeded) and „Fehlgeschlagen“ (Failed) here but via „Abschließen“ (Close) (see Closing a project).
- Observe the rules when changing.
| Change | What happens |
|---|---|
| Within the early phases, forward from „Umsetzung“ | The phase is set directly. |
| From an early phase to „Umsetzung“ | Instead of switching directly, the project optimization opens; only „Übernehmen“ (Apply) sets „Umsetzung“ (needs access to optimization). |
| Back to an early phase after an optimization was applied | Warning „Optimierung verwerfen?“ (Discard optimization?). The reversion removes future bookings and open procurement requests of the optimizer and resets the scheduling; past items and your own changes are kept (needs access to optimization). |
| Back without a previous apply | The phase is set directly. |
Result
Section titled “Result”A documented gate decision and a project phase that consistently drives planning, scoreboard and portfolio view.
See also
Section titled “See also”Project lifecycle · Closing a project & lessons learned · Identifying a risk → managing the measure