Optimization run (optimization_run)

An optimization run is a computed schedule for one or more projects that you can review, commit and roll back again.

The Optimization run (optimization_run) stores one computation of the optimizer: the input (tasks, dependencies, scheduled people with availability, equipment, material demand, calendar), the status and – via the Optimization result (optimization_result) – the solved schedule. For each participating project a Run membership (optimization_run_project) records whether the project was solved, whether and when its result was committed and how many booking conflicts were detected in the process. Only committing writes the schedule into tasks, bookings and procurement. (Planning data; held server-side, not shown as a table in the interface)

  • Project optimization: the button „Optimierer“ (Optimizer) in the header of the project view opens the window „Projekt-Optimierung“ (Project optimization) for one project; see Guides › Building & optimizing the work plan.
  • Portfolio optimization: Portfolio › Strategie, select projects, „Optimieren (n)“ (Optimize (n)) opens „Portfolio-Optimierung“ (Portfolio optimization) for several projects (programs are skipped); see Guides › Scheduling a portfolio with the optimizer.
  • Both windows show the views „Zeitplan“ (Schedule), „Projekte“ (Projects), „Ressourcen“ (Resources) and „Material“, the buttons „Neue Optimierung starten“ (Start new optimization) / „Neu berechnen“ (Recompute), „Übernehmen“ (Commit) or „Alle übernehmen“ (Commit all) and the badges „✓ Übernommen“ (Committed) and „Veraltet — neu berechnen“ (Outdated — recompute).
  • The rollback runs via the phase change back to an early phase („Optimierung verwerfen?“ › „Trotzdem zurücksetzen“, Discard optimization? › Reset anyway); see Guides › Gate decision & phase change.

The fields are not shown as a form but evaluated in the windows „Projekt-Optimierung“ / „Portfolio-Optimierung“.

Field Technical Type Required Meaning Notes
Status status Selection yes State of the computation, see States System
Committed on committed_at Date no Time of the commit (single-project run) System; empty = never committed; badge „✓ Übernommen“
Kind kind Selection yes standard (normal run) or scenario (what-if run of an agent) System; scenario runs never appear in the optimizer window and cannot be committed
Label label Text no Short description of a scenario run System, scenario only
Project project_id Reference no Project for single-project runs System

Run membership (optimization_run_project, one row per run and project):

Field Technical Type Required Meaning Notes
Solved solved Yes/No yes Project had plannable tasks and is included in the result System; false → commit refused
Committed on committed_at Date no Commit of this project from this run System; badge „✓ Übernommen“ per project
Booking conflicts booking_conflicts Number no Overlaps with bookings of other runs or manual bookings, detected on commit System; mentioned in the success message, never blocking
Committed scopes applied_flags Selection (multiple) no Which scopes were committed (task positions, task dates, employee bookings, equipment bookings, procurement) System; a repeated commit with the same scopes is refused („already applied — roll back first“)
State before commit pre_commit_snapshot – no All values that the commit overwrites System; basis for the rollback

The result (optimization_result.result) is resolved server-side into calendar dates and shown in the window:

Content Display
Per project: achieved end, desired end, delay (working days), costs KPIs „Enddatum“ (End date), „Ziel“ (Target), „Verspätung“ / „Termingerecht“ (Delay / On time), „Puffer“ (Buffer), „Kosten“ (Costs), „Gesamtaufwand“ (Total effort), comparison „Aktueller Plan → Optimierter Plan“ (Current plan → Optimized plan; „Dauer“, „Parallelität“, „Zuweisungen“)
Per task: start, end, assigned resources (people, unfilled roles, equipment) „Zeitplan“ (bars, markers „Zieltermin“, „Gate“, „Meilenstein“, „Termin“), chips „verschoben“ (shifted) / „Buchungen“ (bookings)
Order proposals (good, quantity, order date, costs) „Bestellvorschläge“ (Order proposals) with „bestellen bis“ (order by), KPI „davon Bestellungen“ (of which orders); view „Material“ with „Benötigt ab“ (Needed from), „Lücke“ (Gap), „Deckung“ (Coverage), status „Verfügbar“ / „In Beschaffung“ / „Beschaffung nötig“ (Available / In procurement / Procurement needed)
Bottlenecks and problems (errors, warnings) „Engpässe“ (Bottlenecks), „Engpass-Ressourcen“ (Bottleneck resources), „Probleme / Zu beheben“ (Problems / To fix), „Ressourcen-Auslastung“ (Resource workload; heatmap)
Position of gates, milestones and events „Gates, Meilensteine & Termine“, KPIs „Gates gehalten“ (Gates held), „Meilensteine gehalten“ (Milestones held)
Solver statistics (computation time, target delay, costs) „Status“, „Rechenzeit“ (Computation time), „Ziel-Verspätung“ (Target delay), „Kosten (Ziel)“ (Costs (target))
Diagnosis on infeasibility „Nicht lösbar“ (Not solvable), section „Diagnose“ with „Belegt“ / „Vermutung“ (Proven / Assumption), „Eingabe-Probleme“ (Input problems), „Ohne Fixierungen neu berechnen“ (Recompute without pins)
Related to Kind Required On archive On delete
Optimization result (optimization_result) has one no – managed server-side
Run membership (optimization_run_project) has many yes (at least one project) – managed server-side
Project (project) n:m via run membership yes – A project with a committed run cannot be deleted; roll back first (restrict, conditional)
Employee/equipment booking, procurement request has many (via optimization_run_id) no – Rows created by the optimizer carry the run ID; they are replaced on a repeated commit and withdrawn on rollback
Value Label in the interface Set by
solving „Optimierung läuft…“ (Optimization running…) Start („Neue Optimierung starten“, „Neu berechnen“)
done Result is shown; solver status e.g. „Termingerecht“ / „Verspätung“ Optimizer worker delivers a solvable result
infeasible „Nicht lösbar“ + „Diagnose“ Worker finds no feasible plan
failed „Letzter Versuch fehlgeschlagen — angezeigt wird der letzte erfolgreiche Lauf.“ Error in the workflow
Start ──▶ solving ──▶ done ──(commit)──▶ committed_at set ──(phase back)──▶ committed_at empty
├──▶ infeasible
└──▶ failed

A run that stays in status solving unusually long is considered aborted („Letzter Versuch läuft ungewöhnlich lange oder wurde abgebrochen …“). As long as a run is in progress for one of the selected projects, no further run can be started.

  • Start: a run covers 1 to 50 projects. The optimizer plans with dependencies, the scheduled people including availability and absences, equipment, material demand and lead times as well as the bookings of other projects as occupied capacity. It does not match skills. The objective is the planned project end; with several projects the optimizer weights a project’s delay by its priority rank (prioritization_rank): a higher rank value means more weight, a missing rank counts as 1.
  • Commit (per project, default scope all five scopes; see Optimizer commit):
    • Tasks and segments receive new positions in the plan and scheduled start/end dates; gates, milestones and events are shifted accordingly; the task’s assignee follows the booking.
    • For every solved assignment, employee and equipment bookings are created with the run ID. Earlier optimizer bookings on the project are replaced; manual bookings remain untouched. Overlaps with foreign bookings are counted and reported, not prevented.
    • The order proposals become open purchase requests („Einkaufsaufforderung“, status „Offen“) with „Frühstens am“ (arrival) and „Fällig am“ (order, taking the article’s lead time into account). Earlier open optimizer requests of the project are replaced; in multi-project runs the project that commits first orders a good, later ones skip it.
    • The planned project period is set to the solved period, the phase changes from „Initialisierung“, „Definition“ or „Planung“ to „Umsetzung“ (forward only). On the phase change Aligia freezes the EVM baseline.
    • The commit is refused for projects in „Abschluss“, „Erfolgreich Abgeschlossen“ or „Fehlgeschlagen“, for unsolved projects, for outdated runs (there is a newer run: „Veraltet — neu berechnen“) and for already committed scopes.
  • Rollback (phase change back to an early phase, needs access to optimization): all committed runs of the project are rolled back from newest to oldest. Optimizer bookings from today onward are removed, those running across the cutoff date are truncated at that date, open optimizer requests are withdrawn, positions, dates and assignments are reset to the state before the commit – only where the value still equals the one written by the commit; your own later changes remain. The EVM baseline is released, committed_at is cleared. The past is preserved. If there is no committed run, Aligia only changes the phase.
  • Projects with a committed run cannot be deleted; the rollback must come first.

Optimizer dates are the source for „Feste Termine“ (Fixed dates) and the planned project period, which enter progress and date KPIs; see Ch. 13 › Progress and Ch. 13 › EVM.

Optimizer commit · Phase rules · Task · Employee booking · Equipment booking · Procurement request · Guides › Scheduling a portfolio with the optimizer