The resource workload shows for all employees and equipment in which projects they are deployed, when they are unavailable and how heavily they are loaded.

Here you identify overload and conflicts across all projects, for example a person who is scheduled in two projects at the same time.

Projekt & Portfolio › Ressourcenauslastung (menu group „Multiprojektmanagement“, across portfolios). At the top right you choose between „Mitarbeiter“ (employees) and „Equipments“.

  • Workload: scheduled hours ÷ available hours. Available are the hours according to the work calendar minus absences.
  • Resource conflict: „Doppelbuchung“ (double booking, two bookings at the same time), „Gebucht & abwesend“ (booked & absent) for employees or „Gebucht & Ausfall“ (booked & unavailable) for equipment.

Each row is a resource. Under each person, the projects in which they are a member as well as their absences are shown as bars. Running projects (phase „Umsetzung“, Execution) with fixed dates are taken into account. A curve shows the workload over time. One value summarizes it for the period from the last 30 days up to a maximum of one year ahead. The colors follow a traffic light.

At the top a summary appears, for example „5 Ressourcenkonflikte bei 3 Mitarbeitenden“ (5 resource conflicts for 3 employees). It opens a list of all conflicts from today on, with overlapping hours and a jump to the affected task („Aufgabe öffnen“, open task). A help icon explains the calculation.

The equipment view works the same way: booking hours per device, unavailabilities such as „Wartung“ (maintenance), „Störung“ (malfunction) or „Reserviert“ (reserved) and conflicts.

Resolving a resource conflict