Guides
Creating a project
From the idea to the classified project: master data, classification in the portfolio and optionally a technical structure.
A new project exists in Aligia, is assigned to a portfolio (and optionally a program), has a project manager and is in the „Initialisierung“ (Initialization) phase.
Who is involved
Section titled “Who is involved”- Project manager – typically creates the project.
- Portfolio manager/PMO or program manager – classify and prioritize.
- Engineer/technician – supplies the technical structure if needed.
Prerequisites
Section titled “Prerequisites”- At least one portfolio exists (see Setting up a new portfolio).
- The future project manager is recorded as an employee in the master data.
- Optional: a suitable project type and a prepared technical structure.
The workflow
Section titled “The workflow”- Choose the entry point. The creation dialog „Neues Projekt“ (New project) can be reached from several places: under Projekt & Portfolio › Projekte & Programme (Project & Portfolio › Projects & Programs), in the portfolio view, in the program view, on the page of a project type and in the Multi-project board. Depending on the entry point, portfolio, program or project type are already pre-filled.
- Define the project identity. The section „Projektidentität“ (Project identity) contains title, „Schlüssel“ (Key, short identifier), „Projekttyp“ (Project type), „Projektleiter“ (Project manager) and a color. Title, key and project manager are required.
- Classify organizationally. Under „Organisatorische Einordnung“ (Organizational classification) you choose the portfolio (required), optionally a program within this portfolio and a rank for the „Priorisierung“ (Prioritization).
- Set the frame. „Standort“ (Location), „Zeitplan & Kapazität“ (Schedule & capacity: planned start, planned end, working days per week, working hours per day) and „Budget & Wirtschaftlichkeit“ (Budget & financial performance: currency, „Budgetziel“ (Budget target), „Wirtschaftlicher Nutzen“ (Economic benefit), probability of success, „Interner Zins“ (Internal interest rate)). Under „Beschreibende Daten“ (Descriptive data) follow description, project scope, consequences of non-fulfilment and specification.
- Optional: customer order and tech structure. If the project is an external order, you record a „Kundenauftrag“ (Customer order). Via „Tech-Struktur“ (Tech structure) you link an existing technical plant structure (see Technical structure); this can also be done later in the „Engineering“ tab.
- Check the result. The project opens with the Scoreboard. You continue to maintain the master data in the Project profile.
Result
Section titled “Result”A project in the „Initialisierung“ (Initialization) phase, visible in the portfolio, in the program if applicable, and in the Multi-project board. Planning can begin.
See also
Section titled “See also”Project view · Building & optimizing the work plan · Evaluating & prioritizing a project idea · Project lifecycle