Dependency (project_item_dependency)

A dependency links the start or end of one planning object to the start or end of another; it controls the order the optimizer respects.

Dependencies link tasks, milestones and gates. The source (source_id) is the predecessor, the target (target_id) the successor. (Data type: planning data, work plan)

Task/Milestone/Gate › context menu or side panel › „Abhängigkeiten“ (Dependencies) › „Neue Abhängigkeit“ (New dependency; search object, choose type); in the Gantt by dragging from connection point to connection point, remove with Del. See Guides › Gantt.

Field Technical Type Required Meaning Notes
Type type Selection yes Linked anchors, see table Default „Ende zu Start“ (End to start)
Depends on source_id Reference (Task/Milestone/Gate) yes Predecessor
Target target_id Reference (Task/Milestone/Gate) yes Successor; the object from which the dialog was opened
Value Label Meaning
end_start Ende zu Start Predecessor must end before successor starts (FS, default)
start_start Start zu Start Predecessor must start before successor starts (SS)
end_end Ende zu Ende Predecessor must end before successor ends (FF)
start_end Start zu Ende Predecessor must start before successor ends (SF, rare)
Related to Kind Required On archive On delete
Predecessor / successor (Task, Milestone, Gate) reference without foreign key yes – dependency is deleted along as soon as one endpoint is deleted
  • No automatic shifting: if a predecessor is moved in the Gantt, the successor does not move with it; a dependency does not shift anything by itself from Execution on either. It is a constraint for the optimizer, which respects all four types and reconciles the plan on the next computation.
  • The Gantt shows dependencies as arrows; there is no critical path.
  • An object cannot depend on itself (locked in the dialog).

Task · Optimization · Guides › A date slips → readjust