Monitoring the program budget

Check budgets and costs of all projects regularly and detect overruns early.

You know how much budget is still free in the program and which projects need to take corrective action.

Program manager, project manager, portfolio manager/PMO.

The projects maintain budgets, budget requests and costs under Financial performance.

  1. Check totals – in the Budget tab, the cards show remaining budget, actual costs, planned costs and forecast remaining budget of the program.
  2. Find outliers – rows highlighted in red show projects over budget. The columns „Abw.“ (Dev.) and „% Abw.“ (% Dev.) show by how much.
  3. See requests – the columns „Genehmigt“ (Approved) and „Beantragt“ (Requested) show open budget requests. Approval is an organizational task and takes place in the project.
  4. Jump into the project – double-clicking a row opens the project’s financial performance. There you clarify causes with the project manager.
  5. Cross-check financial performance – in the Business case you see whether the program still pays off despite the additional costs.

Budget risks are known and assigned to the projects. The figures feed into the next program report, there into the Costs area.