Gantt
The schedule of the program: one program bar with the bars of its projects.
What it is for
Section titled “What it is for”The Gantt shows how the projects of the program are positioned in time relative to each other and which period the program covers as a whole.
Where in the app
Section titled “Where in the app”Program view, tab „Gantt“. General operation is explained on the tool page Gantt.
Key terms
Section titled “Key terms”- Plan mode: shows projects in early phases (Initialization, Definition, Planning). Their dates are still planned relatively.
- Actual mode: shows projects with fixed dates. These dates only come into being when the schedule is firmly adopted.
How it works
Section titled “How it works”At the top right you switch between „Plan-Modus“ (Plan mode) and „Ist-Modus“ (Actual mode). The program appears as a parent bar, the projects as bars below it.
- In plan mode, projects in early phases appear normally. Projects with fixed dates are shown in grey with the suffix „(Ist)“ for orientation. If no project is in an early phase anymore, plan mode stays empty.
- In actual mode, projects with fixed dates are placed at their actual period. Projects in early phases appear in grey with the suffix „(Plan)“. They are shown starting from their planned start.
If the program has its own fixed dates, these determine the program bar. Otherwise it results from the projects.
Interplay
Section titled “Interplay”- The project bars reflect the work plan of the projects (Work area).
- For all programs and projects of a portfolio there is the Multi-project board.