Reference & Data Model
Strategy & prioritization
KPIs of the portfolio prioritization: rank, success probability, target and risk contribution, and the charts of the strategy view.
All values on this page are calculated in the view.
| KPI | MP | PF | PG | PJ | Where | Meaning | Calculation | Display |
|---|---|---|---|---|---|---|---|---|
| Prioritization / prio score („Priorisierung“ / „Prio-Score“) | ✓ | ✓ | ✓ | PF: Strategy › table (rank changeable by dragging), strategy fit „Top-Priorität“, Preparation › column, profile cards; PG: Profile › badge/quick stats, Planning objects › column; PJ: Profile › header | Manually assigned rank from the portfolio prioritization | Project: field prioritization_rank. Program: Ø of the child projects (0 decimals); 0 projects → „NaN“ (PG profile) or „-“ (table) |
Number · badge | |
| Success probability („Erfolgswahrscheinlichkeit“) | ✓ | ✓ | ✓ | PF: Strategy › table „Erfolg (%)“ + footer Ø, radar, profile cards; PG: Profile, project cards; PJ: Profile › header | Manually maintained success probability | Direct field success_probability_in_pct (project or program), 0 decimals; 0/empty → „-%“; radar sets programs to 0 |
% | |
| Target contribution („Zielbeitrag“) | ✓ | ✓ | PF: Strategy › table (+ Ø footer), priority matrix (X), strategy fit › card 1; PJ: Profile › header, Insights › „Ziel- & Risikobeitrag“ | Weighted share of fulfilled portfolio targets | Only assessments of active portfolio targets: Σ weighting of the „Ja“ answers ÷ Σ weighting of all assessed × 100; nothing assessed → 0. Program: assessments of all sub-projects pooled | % · bar (0–100) / number | ||
| Risk contribution („Risikobeitrag“) | ✓ | ✓ | PF: Strategy › table (+ Ø), priority matrix (Y); PJ: Profile › header, Insights | Weighted share of affirmed risk criteria (higher = more risk) | Like target contribution over active risk criteria and their assessments | % | ||
| Ø portfolio (target contribution) („Ø Portfolio“) | ✓ | Portfolio › Scoreboard › strategy fit › card 1 | Unweighted average of the target contributions | Σ target contribution ÷ number of top-level elements | % · dashed line | |||
| Top priority („Top-Priorität“) | ✓ | Portfolio › Scoreboard › strategy fit › card 3 | Five elements with the highest prio score | Project: rank; program: Ø of the sub-projects; top 5 descending | Ranking list + number | |||
| Priority matrix („Prioritätsmatrix“) | ✓ | Portfolio › Strategy › card 1 | Positioning by strategy fit | X = target contribution, Y = risk contribution (0–100); bubble size = benefit (program Σ children) | Scatter plot | |||
| Costs vs. benefit (bars) („Kosten vs. Nutzen“) | ✓ | Portfolio › Strategy › card 2 | Outflows and inflows per element | Left (negative): total costs (prioritization), probable damage; right: order volume (with an order) otherwise benefit, probable success; order by rank | € · stacked bars | |||
| Radar („Gesamtkosten“ / „Auftragsvolumen“ / „P(Schaden)“ / „P(Erfolg)“ / „Erfolg“ / „Dauer“) | ✓ | Portfolio › Strategy › card 3 | Comparison of the selection relative to the respective maximum | Axes: total costs (prioritization), order volume, probable damage/success, success probability (program 0), duration in calendar years | Radar (6 axes) | |||
| Σ total (prioritization footer) („Σ Summe“) | ✓ | Portfolio › Strategy › table › footer (selection or all) | Aggregate of the selected elements | Σ value = Σ expected income − Σ total costs; ROI = Σ value ÷ Σ costs × 100 (0 at costs 0); Σ benefit, Σ order volume, Σ costs, Σ P(damage)/P(success); Ø target contribution/risk contribution/success (unweighted, success incl. programs); Ø duration; Σ effort | € / % / d / h | |||
| Criteria › weighting („Kriterien › Gewichtung“) | ✓ | Portfolio › Criteria (target and risk criteria) | Relative weight of a criterion in the target/risk contribution | Attribute „{n}x“; status Aktiv/Inaktiv (inactive ones do not enter) | Number + badge | |||
| Value vs. risk (scatter plot) („Wert vs. Risiko“) | ✓ | Portfolio › Scoreboard › „Balance“ | Position of the top-level elements by value and expected damage | X = probable damage, Y = value (prioritization), bubble size ∝ total costs (prioritization); labels only for top 3 by value | € axes · bubbles |
- Target contribution without assessment shows 0 %, not „—“. A project without assessments is therefore indistinguishable from a project with nothing but „Nein“ answers.
- Priority matrix: the bubble size is the benefit from the profile, not the expected income. A project with an order but without benefit is the smallest bubble.
- Footer: „Ø Erfolg“ also averages programs, the radar sets programs to 0; footer ROI shows „0 %“ at costs 0, rows „–“.
- Program profile shows „NaN“ as prioritization at 0 projects.
See Portfolio target, Risk criterion, Guides › Strategy, Guides › Criteria.