Guides
Identifying a risk → managing the measure
Assess risks, back them with preventive and reactive measures and track their effect and costs.
Every relevant risk is assessed, has an owner and measures whose effect on the probability of occurrence is visible.
Who is involved
Section titled “Who is involved”- Project manager – records and manages.
- Risk owners (in the field „Risiko-Administrator“) – drive individual risks; this is a descriptive assignment.
- Program manager – sees the risks across projects (see Managing program risks).
Prerequisites
Section titled “Prerequisites”- The project is created; cost types exist for measure costs.
The workflow
Section titled “The workflow”- Record the risk. In the „Risiken/Chancen“ (Risks/Opportunities) tab you describe the risk with possible damage, probability of occurrence, damage extent and consequences. You record opportunities in mirror image in the „Chancen“ (Opportunities) section.
- Classify. The risk/opportunity matrix compares severity and probability and shows where action is needed.
- Plan measures. Under „Präventive Maßnahmen“ (Preventive measures) you lower the probability of occurrence in advance. „Reaktive Maßnahmen“ (Reactive measures) take effect on occurrence. Each measure has a responsible person, costs, cost type and a percentage risk mitigation. Measures can also be assigned to a gate.
- Track implementation. Measures switch between open, done and „Verworfen“ (Discarded). The totals show the „Verringerung insgesamt“ (Total reduction) and the „Maßnahmenkosten“ (Measure costs). Measure costs appear as system-generated bookings in the budget plan.
- Document occurrence. If a risk occurs, you record the date and the actual damage. This also flows into the financial performance as costs.
- Evaluate across the project. Under „Projekt-Insights“, „Maßnahmen & Initiativen“ (Measures & initiatives) bundles all measures of the project with total costs.
Result
Section titled “Result”A managed risk register with traceable effect and costs that feeds into the status report („Risiko/Chance“ area).
See also
Section titled “See also”Risk matrix · Gate decision & phase change · Creating a status report